MyClearwater.com - The Official Web Site of the City of Clearwater, FL
Search the Site
Home Information Services Activities Government Employment
Site Map | Español | Contact Us
bullet City Manager bullet Mayor & City Council bullet City Departments bullet Codes/Charter bullet Public Records
City Home > Government > City Departments > Engineering > Projects > Engineering Projects Details

Engineering Department

Engineering

Divisions:
Invitation to Bid /
City Projects

Plan Room Program Tutorial Video

Engineering Projects

Expected Road Closures

Contact Department

Engineering Project Details

Information about Engineering Projects is provided with the latest updates available. Please contact the Engineering Department at (727) 562-4750, if more information is required.

General Information:
Project Status: Pre-Design Phase
Project Title: MORNINGSIDE RECLAIMED WATER SYSTEM
Project Number: 05-0022-UT
Project Location: Morningside Subdivision Area, also Hercules Ave., Lakeview Rd. and Corbett St. (Belleair Country Club Area).
Project Description: The Morningside Reclaimed Water (RCW) Project was approved for grant funding in 2004 and design was completed in November 2006. Due to lower than anticipated residential interest in reclaimed water within the service area, mostly due to existing irrigation sources such as wells and lake withdraw, the project has been placed on hold. Subsequently, to encourage support and to provide education on benefits of reclaimed water, the City has attended homeowner association meetings, initiated irrigation source surveys and distributed customer questionnaires to better understand the service area. Recent survey results and feasibility studies have led to a revised service area that will meet the criteria of the Cooperative Funding Agreement between the City and the Southwest Florida Water Management District (SWFWMD).

The revised service area requires the connection of several large users to meet the criteria including Clearwater High School, Church of Christ, Masonic Lodge, Rousseau Cemetery, Plumb Elementary School, Oak Grove Middle School and Belleair County Club (BCC). With the exception of BCC, these large users are located between the Skycrest and Morningside Service Areas. As such, this project involves approximately 7,800-linear feet (LF) of 8-inch transmission main to be constructed between the two service areas to provide RCW service to the large users and to provide a “looped” system between the east and west RCW systems. Further, this project involves the construction of approximately 2,260-LF of 8-inch transmission main to serve BCC and 2,400-LF of 4-inch distribution piping that will serve Oak Grove Middle School and the residences along Morningside Drive.

To provide service to the BCC, this project will also require a flow control station within City Right-of-Way (ROW) along Corbett Street and a Utility Easement from said ROW to a new outfall box where the RCW will be discharged into a storage pond and utilized for irrigation by the BCC Golf Course.

Upon completion of the design, the transmission main, distribution piping, flow control station and outfall structure will be incorporated into the Morningside Contract Documents for bidding purposes.
Project Manager: Kelly J. O'Brien
Consultant: McKim & Creed
Contractor: TBD
Project Notes:  
Anticipated Schedule:
Design Phase: Bid Phase: Award
Date:
Construction Phase:
Start: End: Start: End: Start: End:
June 2008 March 2009 May 2009 July 2009 October 2009 January 2010 November 2010
[ Previous Page ] [ Top of Page ]
City Home | Information | Services | Activities | Government | Employment
Site Map | Español | Contact Us
Privacy Policy & Legal Notices
Page last updated Thursday, June 26, 2008

City of Clearwater Logo
©2006 City of Clearwater