Task Name |
Start |
Finish |
% Work Complete |
| 2.1 Project Management & Coordination | 6-Mar-00 |
01-Jun-01 |
100% |
| 2.1.1 Project Management Plan | 06-Mar-00 |
17-Mar-00 |
100% |
| 2.1.2 Kickoff Meeting | 17-Mar-00 |
17-Mar-00 |
100% |
| 2.1.2 Project Coordination | 06-Mar-00 |
01-Jun-01 |
100% |
| 2.2 Information Collection & Management | 20-Mar-00 |
12-May-00 |
100% |
| 2.2.1 Literature Search | 20-Mar-00 |
21-Apr-00 |
100% |
| 2.2.2 Eval. & Define Deficiencies of Exist. Data | 27-Mar-00 |
12-May-00 |
100% |
| 2.3 Field Work & Data Analysis | 20-Mar-00 |
27-Oct-00 |
100% |
| 2.3.1 Field Work | 20-Mar-00 |
09-Jun-00 |
100% |
| 2.3.2 Biological Resources | 20-Mar-00 |
21-Jul-00 |
100% |
| 2.3.3 Water Quality Analysis | 03-Apr-00 |
16-Oct-00 |
100% |
| 2.3.4 Land Use Inventory | 20-Mar-00 |
07-Apr-00 |
100% |
| 2.3.5 Surveying | 22-May-00 |
14-Aug-00 |
100% |
| Prepare & Submit Watershed Pollutant Loading Interim Report (WPLIR) | 01-Feb-01 |
14-Feb-01 |
100% |
| Rev. & Approv. WPLIR |
15-Feb-01 |
01-Mar-01 |
100% |
| 2.3.6 GIS Database | 20-Mar-00 |
04-Aug-00 |
100% |
| 2.4 Watershed Modeling | 10-Apr-00 |
9-Oct-00 |
100% |
| Hydrologic Model Development | 10-Apr-00 |
26-May-00 |
100% |
| Hydraulic Model Development | 17-Jul-00 |
22-Sep-00 |
100% |
| Model Calibration | 25-Sep-00 |
9-Oct-00 |
100% |
| Prepare & Submit Interim Report | 9-Oct-00 |
25-Oct-00 |
100% |
| Review & Approval of Interim Report | 25-Oct-00 |
9-Nov-00 |
100% |
| Prepare & Submit FEMA LOMR Application | 01-Mar-01 |
18-Apr-01 |
0% |
| FEMA LOMR Application Review & Approval | 18-Apr-01 |
17-Jul-01 |
0% |
| 2.5 Identification of Problems & Potential Solutions | 04-Sep-00 |
10-Nov-00 |
100% |
| 2.5.1 Evaluate Existing Conditions | 9-Oct-00 |
25-Oct-00 |
100% |
| 2.5.2 Develop & Eval. Potential Solutions | 02-Oct-00 |
10-Nov-00 |
100% |
| 2.6 Evaluation & Prioritization of Potential Solutions | 13-Nov-00 |
31-Jul-01 |
100% |
| 2.6.1 Eval. & Prioritize Potential Solutions | 13-Nov-00 |
15-Mar-01 |
100% |
| 2.6.2 Preliminary Report | 13-Nov-00 |
14-Feb-01 |
100% |
| Rev. & Approv. of Preliminary Report |
15-Feb-01 |
15-Mar-01 |
100% |
| 2.6.3 Draft Final Report |
19-Mar-01 |
30-Mar-01 |
100% |
| Rev. & Approv. of Draft Final Report | 19-Apr-01 |
30-Apr-01 |
100% |
| 2.6.4 Final Report |
02-Apr-01 |
30-Apr-01 |
100% |
| 2.7 Coordination with Permitting Agencies | 08-Jan-01 |
08-Feb-01 |
100% |
| 2.8 Presentations. Public Meetings & Technical Liaison | 27-Apr-00 |
15-Jun-01 |
100% |
| Meeting with SWFWMD Permitting Dept. |
25-Sep-01 11:00am |
||
| Public Information Meeting No. 2 |
31-Jan-01 |
||
| Public Information Meeting No. 3 |
TBA |
||
| Presentation to City Council |
TBA |
||
| Presentation to SWFWMD & Basin Board No.1 |
TBA |
||
| Presentation to SWFWMD & Basin Board No. 2 |
TBA |
||